Periodic assessment intervals
Read the assessment interval reg 75 and NZS 4512 state.
Reads Electricity (Safety) Regulations 2010 and NZS 4512:2010. Tables checked 26 Sept 2026.
Try a job 6
Each job fills in example values. Replace them with your values.
- Find the inspection interval for a marinaHow often a marina installation must have an assessment in NZ.
- Find the interval for a construction siteThe verification intervals for a construction site.
- Find the interval for a carnivalHow often show wiring must have an assessment.
- Find the interval for a hazardous areaThe inspection standard for a hazardous area.
- Find the interval for a medical areaThe assessment a medical installation must have.
- Find the fire alarm test intervalsThe monthly and annual checks NZS 4512 lists.
Inputs
Worked example with the default inputs. The live calculator replaces it when the page loads.
- Installation type
- Caravan park, low voltage installation
Maximum interval reg 75(1) states, low voltage installation
5 years maximum
- Installation
- Caravan park, low voltage installation
- Standard named
- AS/NZS 3001.1
- Reference
- Electricity (Safety) Regulations 2010 reg 75(1)(a)
- Record of assessment kept for, reg 75(4)(d)
- 3 years
This result is a design aid. Verify it against the current standard.
Calculation steps
- InstallationCaravan park, low voltage installation
Electricity (Safety) Regulations 2010 reg 75(1)(a)
- Standard namedAS/NZS 3001.1
Electricity (Safety) Regulations 2010 reg 75(1)(a)
- Maximum interval reg 75(1) states, low voltage installationResult5 years maximum
Electricity (Safety) Regulations 2010 reg 75(1)(a)
- Record of assessment kept for, years3
Electricity (Safety) Regulations 2010 reg 75(4)(d)
About this calculator
How this is calculated
The tool looks up the periodic assessment interval for a site type. It reads Electricity (Safety) Regulations 2010 reg 75 and points at the standard that reg 75 names.
- Installation. You pick the site type, such as a caravan park. The tool finds its entry in reg 75(1)(a).
- Standard named. It gives the standard that the entry names for the assessment.
- Interval. It gives the maximum interval that reg 75(1) states for a low voltage installation.
- Record. It gives how long the record of assessment is kept, from reg 75(4)(d).
- Fire alarm. For a fire alarm system, it adds the NZS 4512 intervals.
Worked example
- Caravan park. The tool names AS/NZS 3001.1. The maximum interval is 5 years. The record is kept for 3 years.
Limits
The tool points at the regulation. It gives no ruling on a site or a system. Reg 75(2) and reg 75(3) cover who carries out the assessment. Reg 75(8) covers how the intervals sit against the standard. The tool holds none of that detail. It read the regulations as at 15 January 2026. Check for a later version.
Use the result to plan the next assessment. The tool gives the maximum interval the regulation states. A shorter interval can apply to your site, because the owner or an insurer can ask for one. The record of assessment is a separate document. Keep it for the period the tool gives. The tool applies to New Zealand only. It has no Australian interval.
See also: Regulatory pathway, Regulations 57 and 59 explained and Who may do electrical work in NZ.
Questions
Each answer describes what this tool calculates. The result is a design aid. Verify against the current standard.
How often is a caravan park or a boat marina assessed?
Electricity (Safety) Regulations 2010 reg 75(1)(a) gives 5 years as the longest interval for a low voltage caravan park installation. It names AS/NZS 3001.1. Reg 75(1)(b) gives the same 5 years for a low voltage boat marina installation, and names AS/NZS 3004.1. AmpSize reports the figures and rules on nothing.
Why does the tool report no interval for some sites?
Reg 75(1)(c), (e) and (f) state no interval. Each names a standard: AS/NZS 3012, AS/NZS 60079.17 for hazardous area sites other than domestic, NZS 6115 or AS/NZS 3003. Any interval comes from that standard, and AmpSize holds no figure from it. A blank here does not put the installation outside reg 75: see reg 75(5) and reg 75(8).
What about portable equipment intervals?
Those come from AS/NZS 3760 Table 4, by environment and equipment class. Use the AmpSize test and tag tool for them. This tool covers the installations reg 75 lists, and the check intervals in NZS 4512:2010 Part 6.
Is this a ruling on a site?
No. The tool names the regulation or the clause and reports the interval stated there. It assesses no site and it is not legal advice. Reg 75(2), reg 75(3) and reg 75(4) address who carries out an assessment and the record of assessment, and AmpSize holds none of that detail.
How long is the record of assessment kept?
Reg 75(4)(d) states 3 years, and names sending a copy to WorkSafe as the alternative. Reg 75(4)(b) addresses what the record states. Read reg 75(4) for the detail. AmpSize reports the 3 year figure only.
Clauses and tables this tool reads
- Electricity (Safety) Regulations 2010 reg 75Periodic assessment of installations
- NZS 4512:2010 Cl 602Fire alarm monthly checks
- reg 75Periodic assessment intervals for special installations
- Cl 602, Cl 603Fire alarm monthly and annual check intervals
Every clause and table, with how each was verified
Tables last checked on 26 Sept 2026.
Related tools
- Hand-held appliance supplyRead the supply arrangements regs 88 to 89A list.Electricity (Safety) Regulations 2010
- Electrical certification pathwayFind the certification pathway for a job in NZ.Electricity (Safety) Regulations 2010
- Cable size calculatorFind the smallest cable size that passes each check.AS/NZS 3008.1.2AS/NZS 3008.1.1AS/NZS 3000
Was this useful?
A question, or a value that looks wrong? Contact us.