AS/NZS 3000:2018
Table C1
Maximum demand, single and multiple domestic installations
The maximum demand tool reads the demand rule for each load group in a domestic installation, for one dwelling or for a block of living units. The EV charger tool reads group (j)(iv).
Kua manatokotia: pānuitia ki te paerewa tā, whārangi 458–461. I tirohia 19 Sept 2026.
Ngā unit: Current A, Power kW
Ko ēnei ngā uara e tuhia ana e AmpSize. Kāore he kupu o te paerewa e tuhia ana. Whakamanahia ki te paerewa o nāianei.
21 rārangi
| Group | Unit | Single method | Single first | Single first A | Single then per | Single then A | Units min | Units max | Units method | Units base A | Units per unit A | Single percent | Single fixed A | Units fixed A | Units percent | Single ladder | Units ladder | Units first | Units first A | Units then per | Units then A | Units cap |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A(i) | points | first-then | 20 | 3 | 20 | 2 | 2 | 5 | per-unit | 6 | 0 | |||||||||||
| A(i) | 6 | 20 | per-unit | 5 | 0.25 | |||||||||||||||||
| A(i) | 21 | per-unit | 0 | 0.5 | ||||||||||||||||||
| A(ii) | kW | percent | 75 | |||||||||||||||||||
| B(i) | points | first-then | 20 | 10 | 20 | 5 | 2 | 5 | per-unit | 10 | 5 | |||||||||||
| B(i) | 6 | 20 | per-unit | 15 | 3.75 | |||||||||||||||||
| B(i) | 21 | per-unit | 50 | 1.9 | ||||||||||||||||||
| B(ii) | A | fixed | 2 | 5 | fixed | 10 | 10 | |||||||||||||||
| B(ii) | 6 | 20 | fixed | 10 | ||||||||||||||||||
| B(ii) | 21 | fixed | 10 | |||||||||||||||||||
| B(iii) | A | fixed | 2 | 5 | fixed | 15 | 15 | |||||||||||||||
| B(iii) | 6 | 20 | fixed | 15 | ||||||||||||||||||
| B(iii) | 21 | fixed | 15 | |||||||||||||||||||
| C | kW | percent | 2 | 5 | per-unit | 15 | 0 | 50 | ||||||||||||||
| C | 6 | 20 | per-unit | 0 | 2.8 | |||||||||||||||||
| C | 21 | per-unit | 0 | 2.8 | ||||||||||||||||||
| D | kW | percent | 2 | 5 | percent | 75 | 75 | |||||||||||||||
| D | 6 | 20 | percent | 75 | ||||||||||||||||||
| D | 21 | percent | 75 | |||||||||||||||||||
| E | kW | percent | 2 | 5 | per-unit | 0 | 6 | 33.3 | ||||||||||||||
| E | 6 | 20 | per-unit | 0 | 6 | |||||||||||||||||
| E | 21 | per-unit | 100 | 0.8 | ||||||||||||||||||
| F | kW | percent | 2 | 5 | per-unit | 0 | 6 | 100 | ||||||||||||||
| F | 6 | 20 | per-unit | 0 | 6 | |||||||||||||||||
| F | 21 | per-unit | 100 | 0.8 | ||||||||||||||||||
| G(spa) | kW | ladder | 2 | 5 | ladder | 75, 25 | 75, 25 | |||||||||||||||
| G(spa) | 6 | 20 | ladder | 75, 25 | ||||||||||||||||||
| G(spa) | 21 | ladder | 75, 25 | |||||||||||||||||||
| G(pool) | kW | ladder | 2 | 5 | ladder | 75, 25 | 75, 25 | |||||||||||||||
| G(pool) | 6 | 20 | ladder | 75, 25 | ||||||||||||||||||
| G(pool) | 21 | ladder | 75, 25 | |||||||||||||||||||
| H | kW | 2 | 5 | percent | 100 | |||||||||||||||||
| H | 6 | 20 | percent | 100 | ||||||||||||||||||
| H | 21 | percent | 100 | |||||||||||||||||||
| I | points | 2 | 5 | first-then | 0 | 0 | 1 | 2 | 15 | |||||||||||||
| I | 6 | 20 | first-then | 0 | 0 | 1 | 2 | 15 | ||||||||||||||
| I | 21 | first-then | 0 | 0 | 1 | 2 | 15 | |||||||||||||||
| J(i) | kW | 2 | 5 | percent | 50 | |||||||||||||||||
| J(i) | 6 | 20 | percent | 50 | ||||||||||||||||||
| J(i) | 21 | percent | 50 | |||||||||||||||||||
| J(ii) | kW | 2 | 5 | percent | 75 | |||||||||||||||||
| J(ii) | 6 | 20 | percent | 75 | ||||||||||||||||||
| J(ii) | 21 | percent | 75 | |||||||||||||||||||
| J(iii)(spa) | kW | 2 | 5 | ladder | 75, 25 | |||||||||||||||||
| J(iii)(spa) | 6 | 20 | ladder | 75, 25 | ||||||||||||||||||
| J(iii)(spa) | 21 | ladder | 75, 25 | |||||||||||||||||||
| J(iii)(pool) | kW | 2 | 5 | ladder | 75, 25 | |||||||||||||||||
| J(iii)(pool) | 6 | 20 | ladder | 75, 25 | ||||||||||||||||||
| J(iii)(pool) | 21 | ladder | 75, 25 | |||||||||||||||||||
| J(iv) | kW | percent | 2 | 5 | percent | 100 | 100 | |||||||||||||||
| J(iv) | 6 | 20 | percent | 90 | ||||||||||||||||||
| J(iv) | 21 | percent | 75 | |||||||||||||||||||
| K | A | ladder | 2 | 5 | ladder | 125, 75, 50 | 125, 75, 50 | |||||||||||||||
| K | 6 | 20 | ladder | 125, 75, 50 | ||||||||||||||||||
| K | 21 | ladder | 125, 75, 50 | |||||||||||||||||||
| L | A | ladder | 2 | 5 | ladder | 100, 50 | 100, 50 | |||||||||||||||
| L | 6 | 20 | ladder | 100, 50 | ||||||||||||||||||
| L | 21 | ladder | 100, 50 | |||||||||||||||||||
| M | A | assess | 2 | 5 | assess | |||||||||||||||||
| M | 6 | 20 | assess | |||||||||||||||||||
| M | 21 | assess |
Ngā taputapu e pānui ana i tērā (3)
Ngā aratohu me ngā whārangi ako e whakahua ana i tēnei (9)
- Fixed heating maximum demand with Table C1
- Hot water cylinder cable size for a 3 kW element
- Cable size for a 20 A heat pump circuit in summer
- AS/NZS 3000 Tables C1 and C2: demand groups
- Motor full load current: 11 kW 400 V DOL
- Domestic maximum demand with Table C1
- Maximum demand and diversity
- Motor circuits and starting
- PV and inverter basics