Will a heat pump fit a 63 A supply?

Spare capacity calculator

+1 reference

Worked to AS/NZS 3000:2018. Tables checked 1 Oct 2026.

A drawn result card from the Spare Capacity tool: left after the new load 5.09 A.

A new heat pump adds load to a house that already has a supply. You need to know if the main switch has room. This guide finds the room with the spare capacity calculator. The terms are in Maximum demand by measurement and limitation.

The house

  • A single‑phase house with a 63 A main switch at 230 V.
  • A logger on the mains recorded a highest demand of 41 A over 30 minutes, on a cold evening.
  • A calculation for the house gave 36 A.
  • The new load is a heat pump that takes 3.5 kW at a power factor of 0.9.

Step 1. Find the maximum demand by measurement

AS/NZS 3000:2018 Cl 2.2.2(c) lets you take the maximum demand from a measurement. Use the highest demand over a 30-minute period. Record it when the house is busiest.

The calculated demand is 36 A. The recorded demand is 41 A. A measured demand above the calculated one is the maximum demand. The tool uses the larger figure, so the maximum demand is 41 A.

Open the tool with this house.

Step 2. Find the spare capacity

The main switch is 63 A. The spare capacity is 63 − 41 = 22 A.

Step 3. Turn the heat pump into amps

The heat pump current is 3.5 kW ÷ (230 V × 0.9) = 16.91 A. Use the design current from the data sheet if you have it. The plate rating is a safe start.

Step 4. Check that it fits

The maximum demand after the new load is 41 + 16.91 = 57.91 A. That is below 63 A, so 5.09 A is left. The heat pump fits.

ItemValue
Maximum demand41 A
Spare capacity22 A
New load16.91 A
Left after the new load5.09 A

Step 5. Cross-check by limitation

Cl 2.2.2(d) gives a second route. If one circuit-breaker limits the demand, its setting is the maximum demand. For mains and submains, add the settings of the breakers they feed.

  • One breaker. Say a 40 A breaker limits the whole demand. The maximum demand is 40 A. The spare capacity is 23 A. After the heat pump, 6.09 A is left.
  • A sum of breakers. The board feeds 32 A, 20 A, 16 A and 16 A breakers. The sum is 84 A. That is above the 63 A main switch. The spare capacity is −21 A, and −37.91 A is left after the heat pump.

Open the tool with the four breakers.

The sum takes no diversity. A house never runs every circuit at once. So the sum is high, and the measurement is the better evidence. Use the sum when you have no recording.

MethodMaximum demandLeft after the heat pump
Measurement, Cl 2.2.2(c)41 A5.09 A
One 40 A breaker, Cl 2.2.2(d)40 A6.09 A
Sum of four breakers, Cl 2.2.2(d)84 A−37.91 A

What to check next

The tool takes the main switch as the capacity. The supply fuse or the network agreement can be lower. Check both before you commit. Then size the heat pump cable with the cable size calculator and pick the RCD with the RCD selection tool.

For an EV charger on the same board, see EV charger spare capacity on a 63 A main switch. For the demand rules behind a calculated figure, see Maximum demand and diversity.

Subukan gamit ang mga input na ito

Bagong load sa
Kilowatt
Power factor
0.9
Sa phase
L1
Mga phase ng bagong load
Single phase
Bagong load
3.5
Kalkuladong demand bawat phase
36 A
Rating ng main switch
63 A
Naitalang demand, L1
41 A
Maximum demand ayon sa
Pagsukat, Cl 2.2.2(c)
Mga phase
Single phase
Phase voltage
230 V
Buksan ang calculator gamit ang mga input na ito

Ano ang susunod

Ang mga ideyang nasa likod nito

Higit pang worked example

Design aid ang AmpSize. I-verify ang mga resulta laban sa kasalukuyang standard.

Nakatulong ba ito?

May tanong, o may value na mukhang mali? Makipag-ugnayan sa amin.